Variation recovery
Rework caused by a client change or an authority comment that no approved variation covers. Reported in hours and money, with the instruction that caused it.
15,430 JOD of delivered work is unclaimed across 1 claim.
All amounts were already in JOD; no conversion applied.
Abdoun Villa Compound
DAO-201
15,430 JOD
340 hours
340 hours of rework since 2026-03-09, traced to Jordan Housing Investment’s cladding specification change — abdoun villa compound of 2026-03-09. No variation raised. 15,430 JOD unclaimed.
Instruction: Cladding specification change — Abdoun Villa Compound — Jordan Housing Investment, 2026-03-09
/Projects/DAO-201/05 Correspondence/2026-03-09 Client cladding change.emlfrom 2026-03-09 to 2026-04-22Affected deliverables: 1
Mizan assembles the claim. A named human reviews and sends it — Mizan never does.
Rework caused by internal error is excluded — that is the firm’s own cost and never claimable. A variation that was submitted but not approved does not count as cover.