Abdoun Villa Compound
DAO-201 · JOD
Abdoun Villa Compound is behind: 52.9% delivered against 92.9% of fee consumed, a health gap of -40 points, and a projected margin of -75.7%.
340 hours of that is rework no variation covers, worth 15430 JOD, traced to Jordan Housing Investment's instruction of 2026-03-09.
Evidence
Progress
52.9%
6 / 14 approved
Fee consumed
92.9%
Health gap
-40.0
master indicator
Margin
-75.7%
WIP
61,486 JOD
delivered, not invoiced
Receivables
0 JOD
oldest 0d
Definition — Health gap: Progress percent minus fee-consumed percent, in percentage points. Positive means the project has earned more of its fee than it has spent; negative means it is burning fee faster than it is delivering. This is the master indicator.
The claim
Unclaimed
15,430 JOD
Hours
340
340 hours of rework since 2026-03-09, traced to Jordan Housing Investment’s cladding specification change — abdoun villa compound of 2026-03-09. No variation raised. 15,430 JOD unclaimed.
Instruction: Cladding specification change — Abdoun Villa Compound — Jordan Housing Investment, 2026-03-09
/Projects/DAO-201/05 Correspondence/2026-03-09 Client cladding change.emlAffected deliverables: 1
Mizan assembles the claim. A named human reviews and sends it — Mizan never does.
Definition — Unvaried rework: Hours booked to rework caused by a client change or an authority comment, where no approved variation covers that instruction, valued at the contracted charge rate for the grade that did the work. Reported in hours and money.
Excludes: Rework caused by internal error, which is the firm’s own cost and never claimable.
Excludes: Rework caused by internal error, which is the firm’s own cost and never claimable.
Confidence and gaps
80% (medium)
- lowest-trust contributing source is legacy-erp (medium)
Timesheets approved to 2026-09-12.
Sources:
legacy-erp · deliverablestimesheet-db · timesheet_entrieslegacy-erp · tasks